Sobrante Water Treatment Plant
The East Bay Municipal Utility District (EBMUD) is actively engaged in the planning phase of the Sobrante Water Treatment Plant (SOWTP) Reliability Improvements Project, located at 5500 Amend Road in El Sobrante, CA. This initiative aims to enhance the treatment capacity of the facility to ensure it meets future water demands and improves water treatment processes during drought conditions.
The project is divided into two phases, with Phase 1 scheduled for construction from the summer of 2039 to the summer of 2043, focusing on immediate upgrades to increase capacity to 60 million gallons per day. Phase 2 will further expand treatment capacity to 80 million gallons per day and is set to commence only if water demand necessitates it, highlighting EBMUD's commitment to sustainable water management and community engagement.